Target set under PMAY-G :Starred Question in Loksabha


Target set under PMAY-G

(a) whether a target has been set for construction of one crore houses in various States in the country under the Pradhan Mantri Awaas Yojana–Gramin (PMAY-G) by the end of 2018-19; 
(b) if so, the facts in this regard; 
(c) whether only 56 lakh houses have been constructed till the end of October, 2018; 
(d) if not, the actual figures in this regard; and 


(e) the names of States where houses have not been constructed as per the set target?

GOVERNMENT OF INDIA

MINISTRY OF RURAL DEVELOPMENT

LOK SABHA

STARRED QUESTION NO: 50                                                             ANSWERED ON: 13.12.2018

Target set under PMAY-G

RAM KUMAR SHARMA KUSHWAHA

Will the Minister of RURAL DEVELOPMENT be pleased to state:-

(a) whether a target has been set for construction of one crore houses in various States in the country under the Pradhan Mantri Awaas Yojana–Gramin (PMAY-G) by the end of 2018-19; 
(b) if so, the facts in this regard; 
(c) whether only 56 lakh houses have been constructed till the end of October, 2018; 
(d) if not, the actual figures in this regard; and 
(e) the names of States where houses have not been constructed as per the set target?

ANSWER

MINISTER OF RURAL DEVELOPMENT
(SHRI NARENDRA SINGH TOMAR)

(a) to (e): A Statement is laid on the Table of the House.

*****

Statement referred to in reply to parts (a), (b),(c),(d) and (e) of the Lok Sabha Starred Question No. 50 for answer on 13.12.2018

(a) to (e) : The erstwhile rural housing scheme Indira Awaas Yojana (IAY) has been restructured into Pradhan Mantri Awaas Yojana-Gramin (PMAY-G) from 01.04.2016. PMAY-G was launched by Hon’ble Prime Minister on 20.11.2016. Under PMAY-G, 1.0 crore houses are targeted for construction over a period of three years from 2016-17 to 2018-19. 

As per data uploaded by the States/UTs on the MIS of PMAY-G, AwaasSoft, 54,35,134 houses have been completed as on 31st October, 2018 under PMAY-G.

A statement indicating State/UT-wise house targeted and constructed under PMAY-G is given at Annexure-I.

Source: Loksabha

PDF/WORD (Hindi)                                                                                         PDF/WORD (English)
Share:

0 comments:

Post a Comment

We are not the official website and are not linked to any Government or Ministry. All the posts published here are for information purpose only. Please do not treat as official website and please don't disclose any personal information here.

Copyright © 2015 Prime Minister's Schemes प्रधानमंत्री योजना. All rights reserved.

Categories

Copyright © Prime Minister's Schemes प्रधानमंत्री योजना | Powered by Blogger Design by ronangelo | Blogger Theme by NewBloggerThemes.com